In what is the largest single investment in AI and digital infrastructure in Europe, Google has pledged $15.1 billion over 2027-2028 in AI and digital infrastructure in Finland. In October 2026, authorities in Finland ordered Google’s subsidiary Tuike Finland to halt environmentally significant prep work at planned data center sites in Muhos and Kajaani, two of the four locations in the project, after reports revealed that Google had already cleared large swaths of forest, completing required environmental impact assessments. Initially, Google—whose dominant, near-monopoly position in general web search and search advertising has held the world hostage for many years—insisted that it acted in good faith under its interpretation of the Forestry Act, but later apologized, acknowledging that “it had fallen short of its own high standards” after clearing roughly 530 hectares, more than 400,000 trees and topsoil, from the two sites.
Despite nature being the victim in this scenario, Google, via its Finnish project company Tuike Finland Oy, decided that an obvious statutory threshold and sequencing rule was not a rule at all; it was simply “preparatory work.” In other words, Google decided that extensive logging, topsoil stripping, excavation, road and storage construction, and drainage were allowable even though it had not received proper approval. Indeed, before required impact assessments (EIAs) were completed, Google carried out large-scale, irreversible site preparation. Along with that, the company underestimated its obligations related to water management on difficult soils, creating a significant public and regulatory crisis in Finland.
Finnish and European Union law demands an EIA for permanent removal or alteration of any continuous area of land above 200 hectares, or roughly 494 acres. Clearly, the purpose of the EIA is to identify and assess negative environmental impacts before any major changes occur so that alternatives, mitigation, or flat-out refusal are still on the table. The Muhos site involved ~330 hectares or roughly 250,000 trees, and Kajaani was just under 200 hectares or roughly 150,000 trees.
With hundreds of thousands of trees destroyed, Google did not simply ignore a vague hint or misunderstand the relevant rules as it cleared land for its massive data centers. In May 2026, the National Licensing and Supervision Authority (LVV) handed the company a clear written decision that a full EIA was required before it could move ahead. But Google went ahead and proceeded with the large-scale land clearing anyway. In fact, logging at Muhos had been underway since March. Tuike requested a formal case-by-case decision from LVV on April 30, 2026, arguing that an EIA might not be necessary at the early stage so that other permits could move forward with no waiting.
But LVV’s reply in May left zero room for ambiguity. It stated that the project did not need a separate decision on whether an EIA was required because it involved permanently clearing over 200 hectares of continuous forest. Thus, it automatically fell under the EIA Act, with the full assessment process applied directly as the law is written.
In its formal response to LVV, submitted around October 12-14, Google’s Tuike claimed that there had been mutual understanding and consensus with authorities in charge that the works underway were in line with the laws and allowed. The company said it had checked with the local building inspector, the Finnish Forest Centre, and LVV, and the work began based on its reading of the rules at the time, leaning heavily on the local Muhos municipality, with which, according to Tuike it had a mutual understanding that the clearing was legal. They each conceded later that the project had not met their own standards.
Small towns like Muhos have multiple reasons to welcome with open arms a project of this size and scale. With just a few thousand residents, a project like this means revenue on many different levels. The town’s mayor publicly described Google’s investment as keeping him quite busy, noting that nothing of that scale has ever existed in Muhos. Along with that, national politicians framed it as good for regional development in northern and eastern Finland. The local building inspector indicated that he approved the work as ordinary preparatory measures under the local Building Act, explaining that he was uncertain how the rules applied and felt pressure from several different directions.
Once the scale of Google’s project became visible, residents in both Muhos and Kajaani spoke out publicly about significant concerns, including brown runoff into streams that feed the Oulujoki River, as well as stripped topsoil, noise on hard ground, and native wildlife moving closer to villages. With no single body specifically in place to stop a company the size of Google from pressuring a small municipality to sell its soul unaware of the dire consequences, the LVV has now got Google’s number. So do the Oulu Police, who opened a preliminary criminal investigation on October 29 into suspected environmental damage at Muhos. The event has made its way into a national debate ahead of the April 2027 parliamentary elections, and the Finnish environment minister has called Google’s blunder a serious matter.
Serious indeed. Some locals have called Google’s aggressive and strategically ignorant approach “American style” with “no sense.” They are not wrong.